C.H.S. Construction Co., Inc v. Mast Construction Services

February 16, 2012

C.H.S. CONSTRUCTION CO., INC., PLAINTIFF-APPELLANT,
v.
MAST CONSTRUCTION SERVICES, INC., DEFENDANT-RESPONDENT.



On appeal from Superior Court of New Jersey, Law Division, Essex County, Docket No. L-321-09.

Per curiam.

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION

Submitted January 23, 2012

Before Judges Ashrafi and Newman.

Plaintiff C.H.S. Construction Co, Inc. (CHS) appeals from an order granting summary judgment to defendant Mast Construction Services, Inc. (Mast) dismissing plaintiff's complaint and entering a judgment for CHS in the amount of $14,596 for payment of outstanding invoice number nine which was not in dispute. We now affirm.

Viewed in a light most favorable to plaintiff, see Brill v. Guardian Life Ins. Co. of Am., 142 N.J. 520, 523 (1995), the background facts may be summarized as follows: CHS agreed to participate with Mast in providing work around the Prudential Center in Newark, New Jersey as part of the Downtown Core District Redevelopment Plan (DCDRP). Mast submitted proposals to do the work, but each of the first two proposals were rejected and the size of the work that was eventually awarded was substantially scaled down. Only the first proposal indicated that CHS was a thirty-five percent participant in the project. The second proposal had CHS as a twenty-percent participant. The third proposal which did not mention CHS as a participant was accepted and represented $1,160,590 in compensation to Mast, which was approximately one-third of the initial bid price.

A May 17, 2007 letter from Ted Domuracki, President of Mast, to Cecil Sanders, President of CHS, notes that a Teaming Agreement had been discussed between Sanders and Mast, but was unsigned. Sanders claimed that an earlier Teaming Agreement did not include the thirty-five percent participation as purportedly previously agreed to and, therefore, he did not execute the agreement. Nonetheless, monthly payments were made and accepted pursuant to the Teaming Agreement in the amount of $7,096, of which $1,096 was a Construction Management Fee to CHS and purportedly reflected CHS's profit on each invoice. There was an hourly increase for CHS's project manager beginning in September 2007 which increased the monthly total to $14,596 as reflected in correspondence of September 25, 2007 and continued through December 2007. The monthly Construction Management Fee of $1,096 remained the same. While no agreement had been signed, the work was performed and payment was accepted by CHS in accordance with Ted Domuracki's correspondence of May 17, 2007 and September 25, 2007 to Cecil Sanders and the correspondence of October 30, 2007 from Cecil Sanders to Ted Domuracki.

CHS maintains that it was entitled to a thirty-five percent participation in the project, regardless of the scaled-down nature of the work, although there was no written agreement solidifying their position. In its complaint, CHS asserted that it was not able to participate to a thirty-five percent share because Mast did not permit CHS to employ the requisite number of employees so that the percentage of the work under the contract could be achieved. In seeking damages for Mast's alleged breach of the oral agreement, plaintiff also alleged in its complaint equitable fraud, legal fraud, negligent misrepresentation, promissory estoppel, equitable estoppel and breach of implied covenant of good faith and fair dealing.

The trial court found that there were no facts to support any fraud. Even assuming, however, that there was a breach of contract despite debatable issues of material fact, the measure of damages would be a loss of profits. Stanley Co. of Am. v. Hercules Powder Co., 16 N.J. 295, 314. Plaintiff submitted nothing in opposition to the motion for summary judgment, enumerating what the loss of profits would be.

Plaintiff sought thirty-five percent of the gross amount of revenues (of $1,268,663.11) that Mast received from the project. CHS maintained that the thirty-five percent of the gross revenues equaled $444,032.08. Subtracting the $93,051 that CHS had been paid to that point, left a balance due of $350,981.08 according to CHS. The trial court pointed out that the total revenues on the project was the wrong measure of damages. The total revenues included the costs that CHS would have had to pay its employees, any benefits, cost of materials as well as any other added expenses. CHS had opportunities through discovery, depositions and by way of affidavit or certification in response to the summary judgment motion, to calculate its purported loss of profits, but did not do so. CHS provided no expert opinion on a projected loss of profits. CHS took the position that it could present the testimony of its owner at trial. The trial court disagreed and granted summary judgment.

On appeal, CHS raises the following issue for our consideration:

POINT ONE

THE MOTION COURT COMMITTED REVERSIBLE ERROR WHEN IT GRANTED MAST'S MOTION FOR SUMMARY JUDGMENT BECAUSE C.H.S. COULD HAVE ESTABLISHED LOST PROFITS WITH A REASONABLE DEGREE OF CERTAINTY THROUGH TESTIMONY BEFORE THE FACT FINDER.

CHS argues that the trial court erroneously granted summary judgment by not allowing CHS to present testimony at trial with respect to the computation of loss of profits. CHS argues that its principal, Cecil Sanders, was not asked how he would do so during discovery nor when he was deposed. CHS asserts that if he were allowed to testify before a fact finder, Sanders would be ...


Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.