Hermes v. Staiano

Decided: September 11, 1981.

FRANCIS X. HERMES AND CONSTANCE HERMES, PLAINTIFFS,
v.
LOUIS STAIANO, EMMA STAIANO, HIS WIFE, AND STAIANO WOOD PRODUCTS, INC., DEFENDANTS



Louis H. Miller, J.s.c.

Miller

This matter comes before the court on defendants' application to dismiss the complaint at the conclusion of plaintiffs' case. The motion was originally made returnable on the day of trial, but because determination of the motion required a fuller exposition of the facts than was before the court at that time, and because determination of the matter required extension of existing law, the application was continued until the close of plaintiffs' proofs. The matter is now ripe for determination.

At this stage of the trial the following facts have been adduced. Sometime during 1969 defendant Staiano Wood Products, Inc., constructed a single-family residence on a lot owned by defendants Louis and Emma C. Staiano, located at 350 Clover Hill Drive, Califon, Hunterdon County. The home was built pursuant to a written agreement and contract of sale with Donald and Susan Brigham. On November 10, 1969 the lot and dwelling that had been constructed thereon was conveyed to the Brighams by the individual defendants.

On or about January 23, 1973 the present plaintiffs, making their first purchase of a residential property, took title to the subject property from the Brighams. Prior to the closing plaintiffs had apparently inspected the property four or five times after having entered into a contract for the purchase of the property in August 1972. The contract called for no inspections of any of the major systems of the home. Plaintiffs actually moved into the home on or about February 1, 1973.

Shortly after taking possession of the premises plaintiffs noticed minor problems relating to the septic system. For example, the kitchen sink would back up when the dishwasher was running, toilets overflowed when flushed while the washing machine or dishwasher were in operation, and on occasion the toilet itself would not function properly. These events occurred on a relatively infrequent basis and seemed to be alleviated when the use of water was curtailed by various conservation procedures.

Plaintiffs also encountered problems with "flooding" in the basement, which led them to cease using the basement area of the dwelling for purposes of storage of personal goods or belongings. This problem increased to the point where there were at one point several inches of water covering the basement floor, at which time plaintiffs contacted their neighbor, a Mr. Telesco, to find out whether the previous owners had had a similar problem. Telesco visited the property and suggested that if the sump pump were turned on, the water would undoubtedly drain from the basement. This required plugging it in, which was promptly done, and as a result of the procedure the basement did in fact drain.

By May 1976 plaintiffs noticed that substantial portions of the backyard became and remained flooded at most times, and the ground surface of the lawn became soggy, spongy and charged with water. On Father's Day in 1976 the septic system refused to take any discharge from any of the water-using devices of the home, as a result of which temporary measures had to be utilized until the septic tank could be dug up and cleared of accumulated effluent. Plaintiffs testified that thereafter more stringent water-conservation techniques were used by them; this alleviated the problem for short periods of time, after which it would become necessary to have the septic tank pumped out again by a professional tank cleaner.

Also, at about that time, plaintiffs first noticed that a horizontal crack had developed in the rear basement wall of the

dwelling. The description of the crack at that time is somewhat vague, but it extended some 10 to 15 feet in length at approximately the middle of the wall and was noticeable.

During March 1978, after a period of severe weather, plaintiffs noticed that some 15 to 18 inches of water had accumulated in the basement and that the sump pump did not appear to be able to handle adequately the total amount of water which was being produced. The water was apparently being introduced into the basement, either through the cinder block walls or through a "French drain" that had been installed around the perimeter of the basement floor at the time of construction. Plaintiffs called the local fire company who pumped out the basement.

Upon inspection of the basement after this procedure plaintiffs determined that the crack in the rear wall of the foundation had increased to some 40 feet in length, with a maximum width of approximately one-sixteenth of an inch at the center. They immediately consulted a professional builder with regard to the crack, as a result of which consultation a complicated system of shoring and bracing was installed in the basement and which remains in place to the present day. This renders a substantial portion of the basement ...


Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.